APPENDIX B

 

 

Preliminary Design Report (PDR) for Morgan WTP, Cleveland, OH

 

 

Water Research Foundation Project #3114:

Innovative Applications of Treatment Processes for Spent Filter Backwash

 

MORGAN WTP RETROFIT

PRELIMINARY DESIGN REPORT

SPENT FILTER BACKWASH EQUALIZATION AND TREATMENT REQUIREMENTS

 


MORGAN WTP RETROFIT

 

 

SPENT FILTER BACKWASH EQUALIZATION AND TREATMENT REQUIREMENT

 

Introduction

 

Pilot studies were conducted at the Garrett A. Morgan Water Treatment Plant (WTP) located in Cleveland, Ohio for Foundation Project 3114 investigating “Innovative Applications of Treatment Processes for Spent Filter Backwash”. City of Cleveland Division of Water (CWD) staff provided logistical and other support to the project team at Environmental Engineering and Technology, Inc. (EE&T) and to two participating manufacturers during pilot studies at the WTP. Findings from these studies are described in the final Foundation project report. The following PDR will summarize: (a) characteristics of existing SFBW treatment facilities at the WTP, (b) findings from the pilot studies by the two manufacturer participants, and (c) cost and footprint estimates for new SFBW treatment facilities at the WTP based on results from the pilot testing. Drawings are included depicting the plan, profile, and other characteristics for the systems on which the cost and footprint estimates are based.

The reader should note that the cost and footprint estimates were based on retrofitting these facilities into the existing SFBW building. This PDR will be part of the Foundation report and consequently may be viewed by other utilities. Consequently, these other utilities need to realize that these estimates are impacted by site specific conditions relative to the retrofit that may not apply to the other utility’s facilities. However, the Foundation report does include a similar PDR for the Utah study site that is more generic and does not involve a retrofit, for utilities to compare alternatives without site specific limitations.

The reader should also note that each manufacturer was only able to conduct testing during one time period. In May 2007 Infilco-Degremont (IDI) evaluated two processes, and Leopold tested one process in September 2007. Since untreated SFBW characteristics were different in the two time periods, the reader should exercise caution in comparing results from one manufacturer to another since they were not compared side-by-side, although it is appropriate to compare the two processes from IDI to one another since they were treating the same SFBW. Furthermore, results are presented in the Foundation report in a separate PDR for studies conducted in Orem, UT. Readers should also exercise caution in comparing results from manufacturers tested at this location versus studies in Cleveland. It would of course be more desirable to conduct testing with one or more processes in multiple time periods in order to evaluate seasonal impacts. However, since both CWD and the two manufacturers donated considerable staff time and equipment just to complete the studiers that were conducted, it was not possible to expect either CWD or the manufacturers to devote additional time to get these multi-seasonal results.

 

Summary of Findings

 

Performance of the pilot tested processes are summarized in Table B.1. Table B.2 summarizes cost and footprint estimates derived from these findings.


Table B.1

Summary of SFBW treatment results discussed in the Foundation report

Process

Median untreated turbidity

(ntu)

Clarification rate

(gpm/ft2)

Residuals concentration

(percent solids)

Information

source

Polymer

needed?

Pilot- or

Full-scale?

95 percent

<2 ntu

March 2000

Standard-rate DAF

20

up to 6

2 to 3

mfr records

yes

pilot

yes

May 2007

AquaDAF

20

16

3

this study

yes

pilot

yes

DensaDeg

20

16

3

this study

yes

pilot

yes

September 2007

ClariDAF

20

15

3.6

this study

yes

pilot

yes

 


Table B.2

Estimated cost and footprint for high-rate SFBW treatment at Morgan WTP

Description

ClariDAF

AquaDAF

DensaDeg

Design conditions

Number of treatment trains

2

2

2

Capacity per treatment train (gpm)

5,200

5,200

5,100

Nominal clarification rate (gpm/ft2)

14

14

10

Flocculation time (min)

16

15

8**

Cost*

Capital ($ million)

8.9

8.7

11.0

O&M ($ thousand/yr)

196

187

225

Net present worth ($ million)H

11.2

10.9

13.6

Footprint (ft2)

Clarification (including all appurtenances)

4,900

3,600

3,300

Additional thickening prior to dewateringI

no

no

no

Clarification rate (gpm/ft2)'

Nominal (i.e., manufacturer)

14

14

10

Relative to footprint

1.06

1.44

1.55

*December 2007 dollars, includes cost of new building and associated appurtenances

H20 years, six percent interest

IAssume thickened solids prior to dewatering have to be >1 percent solids

§One train out of service

**Solids contact time (i.e., detention time in reactor tank)

 

The existing full-scale SFBW treatment facility at the Morgan WTP is rated at a capacity of 3,375 gpm, including 7,000 ft2 of clarification area capable of reliably operating at rates up to 0.6 gpm/ft2.  However, since the WTP filtration capacity is 150 mgd due to high-rate certification of filters at 4.4 gpm/ft2, in order to provide treatment capacity for up to five percent recycle, the new SFBW treatment system will need to be 7 mgd, or about 5,200 gpm. For redundancy, enough treatment should be provided so that new proposed SFBW treatment systems will be able to handle 5,200 gpm of SFBW even with one SFBW treatment train out of service.

The costs and footprint for treatment listed in Table B.2 are based on the five percent recycle assumption, and also include sufficient capacity under these assumptions with one unit out of service (i.e., 100 percent redundancy). The costs for the 10 percent recycle assumptions are not presented, but although there would be some economies of scale possible with the larger treatment facilities needed, it is expected that the cost for the 10 percent assumption would be about 1.5 times the amounts listed in Table B.2 (i.e., one more train, allowing two units in service to handle all required volume with one unit out of service).

In addition to treatment costs, more equalization will be needed as well. The following PDR describes derivation of additional equalization volume needed. The end result is that for the five percent recycle assumption (if 10 percent recycle rate was used instead, the required size of SFBW treatment would increase but required equalization volume would decrease) the total equalization volume needed is 0.91 MG, or about 0.21 MG more than existing. This additional volume can be achieved with an additional 44-ft diameter basin at a capital cost of about $2.45 million, $43,000/yr in O&M, or a net present value of about $3 million (20-year life-cycle, at six percent interest).


Total costs and footprint for the five percent recycle scenario would include requirements for both high-rate treatment and equalization. However, the residuals produced from these three high-rate processes are expected to be >3 percent solids, and consequently should not require additional thickening prior to dewatering. Although costs for SFBW treatment using “conventional” gravity settling, including plates or tubes, are not included in Table B.2, since these processes do produce residuals with about 0.3 percent solids, these processes would require additional thickening to achieve one percent solids or greater prior to dewatering.  Consequently, since the high-rate SFBW treatment options produce so much higher percent solids in the residuals stream, installation of these processes would also avoid the thickening costs required for other processes if residuals are to be sent for dewatering.  Other high-rate processes, for example sand ballasted coagulation or upflow buoyant media clarification, may not produce percent solids as high as the three processes evaluated at Morgan, and consequently costs for thickening should be included when comparing these processes to the above processes.

These results demonstrate that a ClariDAF system with two 5,200 gpm treatment trains designed at 14 gpm/ft2 nominal (i.e., manufacturer) clarification rate and requiring a minimum of 16 minutes flocculation would require an area of 4,900 ft2 within the western portion of the residuals handling building currently housing the SFBW clarifiers. The estimated footprint includes area for all required flocculation, clarification, chemical feed, air saturation, and other assorted appurtenances. Therefore, though nominally a 14 gpm/ft2 system when you consider only clarification area, when you consider the entire footprint impact (including the 100 percent redundancy assumption) the rate expressed relative to the new total treatment area when one train is out of service is 5,200 gpm for a 4,900 ft2 area, or about 1.06 gpm/ft2.

Similar evaluations for the AquaDAF process indicates that the required footprint for two 5,200 gpm treatment trains is 3,600 ft2, or 1.44 gpm/ft2 for the nominal 14 gpm/ft2 process (including 15 min flocculation) when expressed relative to total footprint impact instead of only clarification area. The DensaDeg process assumptions included two 5,100 gpm facilities in order to provide the same redundancy assumption (one train out of service), requiring about 3,300 ft2 for a nominal 10 gpm/ft2 process, or a 1.55 gpm/ft2 clarification rate expressed relative to total footprint impact (with one train out of service).

 

EXISTING FACILITIES

 

            The Morgan WTP located in Cleveland, Ohio, operated by the City of Cleveland Division of Water (CWD), draws source water from nearby Lake Erie. The plant utilizes PAC, chlorine, potassium permanganate, alum coagulation, three-stage flocculation, and sedimentation prior to granular media filtration. It has a capacity of 150 MGD with 28 dual-media filters rated at 4.4 gpm/ft2. Figure B.1 and B.2 are a schematic and site plan for the facility.

Spent filter backwash (SFBW) is treated by a clarifier and recycled to the head of the plant, while the removed solids are discharged to the sanitary sewer. The existing SFBW treatment facilities include two 350,000-gal equalization (EQ) basins, referred to as the “East” and “West” EQ basins. Both basins can pump directly to the sludge holding tank, the SFBW clarifier, or to the head of the main plant.

 

0322 Morgan WTP Process Schematic

Figure B.1  Morgan WTP process schematic

 

 

0322 Morgan WTP Siteplan

Figure B.2  Morgan WTP facilities site plan

Analogous to Figures B.1 and B.2 depicting the entire WTP facility, Figures B.3 and B.4 depict a site plan and schematic for the SFBW treatment and handling portion of these facilities.  SFBW treatment includes equalization (without mixing), a flash mix tank, three-stage flocculation, clarification, and recycle of clarified SFBW to the head of the plant. The SFBW clarifier is vacuumed by a traveling bridge sludge collection system to a 450,000-gal sludge holding tank where it is combined with sludge from the main plant’s sedimentation basins. When necessary, a sludge dilution chamber is used to dilute the sludge to a 0.4 percent solids concentration before being discharged to the sanitary sewer.

 

 

 

0322 Morgan SFBW Siteplan

 

Figure B.3 Morgan WTP SFBW treatment facilities site plan

 

 

0322 Morgan SFBW Schematic

 

Figure B.4  Morgan WTP SFBW treatment facilities schematic

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure B.5  Morgan WTP SFBW full scale clarifier testing

 

 

            Full scale testing of the existing clarifier was conducted in 2000. Morgan WTP’s SFBW was typically around 20 ntu and was effectively treated to <2 ntu at loading rates up to 0.8 gpm/ft2 (Figure B.5) when polymer was applied. Without polymer addition, the treated turbidity ranged from 5 to 13 ntu at loading rates from 0.53 to 0.8 gpm/ft2 respectively. Based on these test results, a conservative maximum loading rate of 0.6 gpm/ft2 with polymer was chosen. Morgan WTP currently does not use polymer for SFBW treatment.

 

 

SFBW EQUALIZATION DESIGN ASSUMPTIONS

 

            Table B.3 lists backwash operation assumptions developed in consultation with CWD for the Morgan WTP.  These operational assumptions were used for calculating the EQ storage volume required and were based on present and future Morgan WTP operations information.

 

Table B.3

Morgan WTP operational assumptions

Maximum filtration rate

3 gpm/ft2

Minimum plant flow rate (5th percentile flow)

55 mgd

Maximum plant flow rate

150 mgd

Recycle rate (10 percent maximum)

5 percent (Partnership for Safe Water)

Backwash volume

260,000 gal/backwash

Backwash frequency interval

30 min/backwash event (1st four filters)

55 min/backwash event (remaining 24 filters)

Backwash duration

10 min

Maximum number of backwashes per day

28

The SFBW EQ basin storage capacity required was calculated using these operational assumptions with the parameters incorporated into a 24-hr storage profile. The results for the assumption with 28 filter backwash events in a 24-hour period (four every 30 minutes in first two hours, than one filter every 55 minutes thereafter) when the Morgan WTP is producing minimum production of 55 mgd are presented in Figure B.6 for three recycle rates (three percent is upper curve, five percent middle curve, and 10 percent lowest curve – dashed line is existing EQ capacity).  The curves in Figure B.7 demonstrate that even if bigger equalization basins were available and even at a recycle rate of 10 percent the plant would never be able to equalize all the SFBW within a 24-hour period (i.e., plant would have to cease all filter backwashing so EQ could be emptied).

Since it was not physically possible to operate the facility under these conditions, a different set of design assumptions were developed, in consultation with CWD. These included assuming a filtration rate of 3 gpm/ft2 (filters are currently permitted at 4.4 gpm/ft2). At this rate, nine filters would be in service when plant is producing 55 mgd, as opposed to the 28 filters assumed to develop calculations in Figure B.6. Table B.4 lists the number of filters needed at this filtration rate under different main plant production targets. Figure B.7 shows the estimated equalization volume needed under similar conditions as used in Figure B.6, except with nine filter backwash events within a 24-hour period instead of 28. At 10 percent recycle, the amount of equalization storage needed is 0.91 MG, or 0.21 MG more than the existing 0.7 MG capacity. An additional 44-ft diameter equalization basin would be required for the additional volume. At lower recycle rates, more equalization is needed. The Morgan WTP operates under Partnership for Safe Water guidelines requiring recycle rates less than five percent. Calculations reflected in Figure B.7 indicate that required equalization at this recycle rate is about 1.62 MG, or about 0.92 MG more than existing equalization. This would require one additional 93-ft diameter equalization basin. If the recycle rate under these conditions is less than five percent, the required equalization is even higher. For example, the predicted equalization storage required for three percent recycle is 1.91 MG, or about 0.3 MG more than at five percent recycle.

Therefore, in order to meet the design assumptions established during conversations with CWD (55 mgd, nine filter backwash events per day, five percent recycle), the required equalization is 1.62 MG, or requiring an additional 93 ft diameter equalization basin to supplement the two existing 0.35 MG basins. Note that this does not make any allowances for redundancy, meaning all equalization basins have to be in service to handle the design condition.

This preliminary design report for CWD will be included in the Foundation SFBW report to be viewed by utilities throughout the US. For those facilities with similar SFBW quantities as the Morgan WTP that will allow recycle rates higher than five percent, the size of equalization will decrease (and size of SFBW treatment (to be discussed below) will be greater).  For example, under the same conditions but with an allowance of 10 percent recycle, the total required equalization is 0.91 MG, or an additional 44-ft diameter basin to supplement the existing basins.

 

SFBW TREATMENT DESIGN ASSUMPTIONS

 

            The above discussion indicated that the design assumption for recycle, and hence for SFBW treatment, is five percent recycle. Consequently, five percent of 150 mgd is 7 mgd, or about 5,200 gpm. For redundancy, enough treatment will be provided so that new proposed SFBW treatment systems will be able to handle 5,200 gpm of SFBW even with one SFBW treatment train out of service.


 

Figure B.6  Morgan WTP SFBW production during 24-hour period assuming 55 mgd production rate, three recycle rates (3, 5, and 10 percent), and 28 filter backwash events per day (0.26 MG per backwash event)

 

 

Figure B.7  Required SFBW equalization assuming 55 mgd production rate, three recycle rates (3, 5, and 10 percent), and nine filter backwash events per day (0.26 MG per backwash event)

 

Table B.4

Morgan WTP filter operations

Plant raw water flow rate

(mgd)

Number of filters in service

@3 gpm/ft2

Total backwash generated

(mgd)

55

9

2.3

65

11

2.9

75

12

3.1

85

14

3.6

95

16

4.2

105

17

4.4

115

19

4.9

120

19

4.9

125

20

5.2

135

22

5.7

145

23

6.0

150

24

6.2

 

28

7.3

 

 

RETROFIT OF MORGAN WTP’S SFBW EQ AND TREATMENT FACILITIES

 

Current operational conditions at the Morgan WTP require additional EQ storage volume for the low flow condition and an increase in clarifier capacity for the high flow condition.  Considering Morgan WTP’s SFBW characteristics and the recent pilot trials by Leopold and IDI, four alternatives were selected for a plant retrofit:

 

            Option A:        Additional EQ storage basin (common to all clarification options)

Option B:        New ClariDAF system by Leopold

            Option C:        New AquaDAF system by IDI

            Option D:        New DensaDeg system by IDI

 

 


Option A:  Additional Equalization Capacity

 

Option A for solving current Morgan WTP operational challenges involves the construction of a new EQ basin. The flow schematic for this option is provided in Figure B.8.  A possible site for this basin is just east of the current EQ basins and is shown in Figure B.9.

 

 

0322 Morgan SFBW Schematic add DAF1

 

Figure B.8  Morgan SFBW schematic with new EQ and new SFBW treatment system

 

 

 

0322 Morgan SFBW Siteplan New EQ

 

 

Figure B.9  Morgan WTP SFBW new EQ siteplan


Table B.5

Morgan WTP SFBW EQ cost analysis for 5 and 10 percent recycle limits

Item

Capital cost

($)

New 0.92 MG EQ basin (5 percent recycle)

4,740,000

New 0.21 MG EQ basin (10 percent recycle)

2,453,000

 

            Capital cost for both a 0.92 MG and a 0.21 MG EQ basin are summarized in Table B.5. Obviously, a considerable cost savings would be attained for utilities that can consider increasing the recycle rate from 5 percent to 10 percent during the rare low flow condition. However, CWD operates the Morgan WTP under Partnership for Safe Water guidelines which limit recycle to five percent or less.

 

Option B:  Retrofit existing clarifier with New High Rate ClariDAF System

 

ClariDAF is a high rate dissolved air flotation system designed by Leopold as depicted in Figure B.10. ClariDAF can be operated at loading rates of 8 to15 gpm/ft2. Clarification rates for this system are based on flow per square foot area occupied by the effluent laterals located at the bottom of the DAF cell. A loading rate defined in this manner does not account for the increased footprint due to the remainder of the system’s components.

The ClariDAF system, as depicted in the schematic in Figure B.11, utilizes a rapid mix zone where polymer may be added followed by one or more flocculation basins and a DAF cell. An internal angled baffle wall create a recirculation effect throughout the DAF cell which increases bubble density and efficient flotation for removal of the “float”. The clarified water exits the system through the laterals and into an effluent channel while the float solids are mechanically skimmed into a collection channel.

Pilot test results from September 2007 are summarized in Table B.6. Based on these results a 14 gpm/ft2 design loading rate and a 16-min flocculation time were used.  Testing also demonstrated that a polymer is required to meet treated water goals of <2 ntu.

            Option B would retrofit the existing 7,000-ft2 clarifier system with two 5,200-gpm ClariDAF systems to meet new SFBW production targets. The new system would have a total footprint of approximately 109 ft by 45 ft or 4,900 ft2 as depicted in Figures B.12 and B.13.  The retrofit would involve renovation of the existing building to include raising the clarifier roof, reconstruction of basin walls, and adding necessary equipment.  Cost calculations are summarized in Tables B.5 and B.6. Costs include construction of concrete roof, walls, ClariDAF equipment, instrumentation, controls, pumps, and a polymer feed system. Plan and profile drawings of the proposed system are depicted in Figures B.12 and B.13.


Clari-DAF schematic

 

Provided by ITT WWW Leopold, September 2007

 

Figure B.10 ClariDAF Schematic

 

 

 

Provided by ITT WWW Leopold, September 2007

 

Figure B.11 ClariDAF Pilot Schematic


Table B.6

Summary of Leopold pilot testing at Cleveland Morgan WTP during September 2007

Duration (hours)

Rate (gpm/ft2)

Recycle (percent)

Floc

time (min)

Polymer dose (mg/L)

Flash mix

Turbidity (ntu)

Particles >2 µm per mL

Untreated

Treated

Treated

Median

Median

Mean

95th perc.

Percent

<2 ntu

Count

Avg

Impact of LT22s polymer dose

2.75

8

11.9

16

0.0

no

6.29

1.61

2.58

7.60

71.9

2

9,148

2.17

8

11.8

16

0.3

no

3.67

0.50

1.33

3.98

74.3

1

1,297

Impact of flash mix

2.17

8

11.8

16

0.3

no

3.67

0.50

1.33

3.98

74.3

1

1,297

3.75

8

12.1

16

0.3

yes

3.96

0.53

0.62

1.58

97.1

1

915

Impact of flocculation time

2.17

8

12.4

0

0.3

yes

3.57

0.65

0.63

0.66

100.0

1

2,439

2.58

8

12.3

8

0.3

yes

4.95

0.50

0.50

0.56

100.0

1

926

3.75

8

12.1

16

0.3

yes

3.96

0.53

0.62

1.58

97.1

1

915

3.83

8

12.3

27

0.3

yes

4.70

0.35

0.57

1.43

100.0

2

805

Impact of clarification rate

3.83

8

12.3

27

0.3

yes

4.70

0.35

0.57

1.43

100.0

2

805

1.83

10

9.8

22

0.3

yes

1.56

0.38

0.43

0.87

100.0

1

1,000

2.00

12

14.0

18

0.3

yes

1.47

0.36

0.38

0.45

100.0

1

1,223

1.83

14

12.2

14

0.3

yes

1.38

0.38

0.38

0.39

100.0

1

1,082

54.25

15

11.6

14

0.3

yes

3.88

0.40

0.42

0.51

99.8

8

1,159

Impact of recycle

1.75

15

4.3

14

0.3

yes

2.71

0.58

0.80

1.94

95.6

1

1,581

1.42

15

6.8

14

0.3

yes

3.15

0.61

0.62

0.67

100.0

1

1,652

54.25

15

11.6

14

0.3

yes

3.88

0.40

0.42

0.51

99.8

8

1,159

 


Table B.7

10 percent SFBW recycle EQ and ClariDAF Retrofit cost analysis

Item

Capital cost

($)

O&M cost

($/yr)

20-yr present worth

($)

New EQ basin (44-ft diameter)

2,453,000

43,000

2,944,000

ClariDAF system retrofit

8,900,000

178,000

11,000,000

TOTAL PROJECT COST

11,353,000

221,000

13,944,000

 

 

Table B.8

5 percent SFBW recycle EQ and ClariDAF Retrofit cost analysis

Item

Capital cost

($)

O&M cost

($/yr)

20-yr present worth

($)

New EQ basin (93-ft diameter)

4,740,000

75,000

5,604,000

ClariDAF system retrofit

8,900,000

178,000

11,000,000

TOTAL PROJECT COST

13,640,000

253,000

16,604,000


Provided by ITT WWW Leopold, September 2007

0322 Morgan ClariDAF System Planview

Figure B.12  Morgan WTP SFBW ClariDAF system plan view

0322 Morgan ClariDAF System ProfileProvided by ITT WWW Leopold, September 2007

 

Figure B.13  Morgan WTP SFBW ClariDAF system profile view


Option C:  Retrofit existing clarifier with New High Rate AquaDAF System

 

Another option for increasing the treatment capacity is to replace the clarifier with a high rate AquaDAF system by Infilco Degremont Inc. (IDI) as shown in Figure B.14.  A second AquaDAF system of equal size is recommended for redundancy purposes. The same EQ basin volume determined for Option A is also required for Option C.  The SFBW flow schematic for this option remains the same as Option A and is provided in Figure B.10.

AquaDAF is a high rate dissolved air flotation system designed by Infilco Degremont, Inc. which can operate at loading rates of 8 to16 gpm/ft2, as piloted in Foundation Project #3114.  Clarification rates for this system are based on flow per square foot area of the false floor at the bottom of the DAF cell. A clarification rate defined in this manner does not account for the increased footprint due to remainder of the system’s components.

The process was developed by the Rictor Company in Sweden and licensed to IDI in 2001.  AquaDAF utilizes dual flocculation chambers where polymer may be added followed by a DAF Cell. An internal angled baffle wall and a false floor create a recirculation effect throughout the DAF Cell which increases bubble density and efficient flotation for removal of the “float”. The clarified water exits the system through a patented hole-patterned piping on the false floor and out an effluent channel while the sludge blanket hydraulically flows over into a collection channel.

 

 

AquaDAF schematic6

Provided by Infilco-Degremont, September 2007

 

Figure B.14  AquaDAF schematic

 

 


            Based on pilot testing results (see Foundation SFBW #3114 Report), a design loading rate of 14 gpm/ft2 with a 15-min flocculation time was used (AquaDAF was successfully piloted with flocculation times <12 min, but 15 min was chosen in order to be conservative). Testing also demonstrated that a polymer is required to meet treated water goals of <2 ntu. Figures B.15 and B.16 include data from the May 2007 pilot studies regarding impact of loading rate on turbidity and particles. In all instances the project goals of median turbidity <1 ntu and 95th percentile turbidity <2 ntu was achieved at all rates tested. However, there was a slight apparent increase in particles at 16 gpm/ft2.

 

 

Note: (0.3 mg/L LT22S, flocculation time from 4.3-8.6 min, ~11 percent recycle)

 

Figure B.15  Impact of AquaDAF loading rates on SFBW turbidity at Morgan WTP

 

Note: (0.3 mg/L LT22S, flocculation time from 4.3-8.6 min, ~11 percent recycle)

 

Figure B.16  Impact of AquaDAF loading rates on SFBW particles at Morgan WTP

 


0322 Morgan AquaDAF System planview

Provided by Infilco-Degremont, September 2007

 

Figure B.17  Morgan WTP SFBW AquaDAF system plan view

Provided by Infilco-Degremont, September 2007

 

Figure B.18  Morgan WTP SFBW AquaDAF system profile view 0322 Morgan AquaDAF System profileview

0322 Morgan AquaDAF System P&IDProvided by Infilco-Degremont, September 2007

 

Figure B.19  Morgan WTP SFBW AquaDAF system P&ID


Table B.9

10 percent SFBW recycle EQ and AquaDAF retrofit cost analysis

Item

Capital cost

($)

O&M cost

($/yr)

20-yr present worth

($)

New EQ basin (44-ft diameter)

2,453,000

43,000

2,944,000

AquaDAF system retrofit

8,750,000

187,000

11,000,000

TOTAL PROJECT COST

11,203,000

230,000

13,944,000

 

Table B.10

5 percent SFBW recycle EQ and AquaDAF retrofit cost analysis

Item

Capital Cost

($)

O&M Cost

($/yr)

20-yr Present Worth

($)

New EQ basin (93-ft diameter)

4,740,000

75,000

5,604,000

AquaDAF system retrofit

8,750,000

187,000

11,000,000

TOTAL PROJECT COST

13,490,000

262,000

16,604,000

 

Option C would retrofit the existing 7,000 ft2 clarifier system with two 5,200 gpm AquaDAF Systems to meet new SFBW production targets. The new system would have a total footprint of approximately 79 ft by 45 ft or 3,600 ft2 as depicted in Figures B.17 to B.19.  The retrofit would involve renovation of the existing building to include raising the clarifier roof, reconstruction of basin walls, and adding necessary equipment.  AquaDAF cost calculations are summarized in Tables B.9 and B.10.

 

Option D:  Retrofit Existing Clarifier with New High Rate DensaDeg System

 

            Another option for increasing the treatment capacity is to replace it with a High Rate DensaDeg System by IDI as shown in Figure B.20.  A second DensaDeg System of equal size is recommended for redundancy purposes. The same EQ basin volume determined for Option A is also required for Option D.  The SFBW flow schematic for this option remains the same as Option A and is provided in Figure B.8.

DensaDeg is a high rate solids contact process designed by IDI which can operate at clarification rates of 8 to 16 gpm/ft2, as piloted in Foundation Project #3114. Clarification rates for this system are based on flow per square foot area occupied by the tube settlers at the top of the clarification basin. A loading rate defined in this manner does not account for the increased footprint due to remainder of the system’s components. This process typically includes a rapid mix module, solids contact in the “reactor” zone following rapid mix, and separation of liquid phase and thickening of solids phase in the “clarification/thickening” zone.  Thickened solids from the clarifier zone are recirculated back into the reactor zone, and the mixer in the reactor promotes solids contact opportunities for the incoming solids in the untreated water along with recirculated solids from the clarification zone.  The rapid mix module is normally used in other studies, but was not used in this study.

 

 

Provided by Infilco-Degremont, September 2007

 

Figure B.20  DensaDeg schematic

 

 

 

Table B.11

Impact of loading rate on DensaDeg performance during May 2007 pilot studies

Test

conditions*

Duration

(hours)

Turbidity (ntu)

Particles >2 µm per mL

Raw

Treated Water

Sample

Median

Median

Mean

95th

Percent

 < 2 ntu

1

2

3

4

5

8 gpm/ft2,

0.25 mg/L, 2.5%

5.5

14.88

0.65

0.65

0.72

100

3,561

2,369

 

 

 

10 gpm/ft2,

0.25 mg/L, 2.5%

7.5

14.57

0.72

0.73

0.86

100

5,216

2,876

2,718

 

 

12 gpm/ft2,

0.25 mg/L, 2.5%

7.1

17.22

0.79

0.78

1.54

100

3,017

12,232

5,471

987

3,083

12 gpm/ft2,

0.25 mg/L, 2.5%

3.1

21.77

0.41

0.46

0.62

100

5,471

    987

3,083

 

 

14 gpm/ft2,

0.5 mg/L, 2.5%

1.5

26.08

0.79

0.76

0.79

100

2,115

1,911

 

 

 

16 gpm/ft2,

0.5 mg/L, 2.5%

2.5

16.05

0.72

0.71

0.86

100

1,805

2,713

5,339

9,353

 

*Rate, polymer dose (LT22s), and percent recycle indicated for each test condition

 


Pilot testing results (see Foundation SFBW #3114 Report), as summarized in Table B.11 and Figure B.21, demonstrated that the process could meet project objectives (median <1 ntu, 95th percentile <2 ntu) at rates up to 16 gpm/ft2, the highest rate tested. Based on these results a loading rate of 10 gpm/ft2 was recommended by the manufacturer. Pilot testing also demonstrated that a polymer is required to meet treated water goals of <2 ntu. (Table B.12 and Figure B.22)

 

 

Figure B.21  Morgan WTP SFBW DensaDeg loading rate for SFBW


Table B.12

Impact of polymer dose on DensaDeg performance during May 2007 pilot studies

Polymer

dose

Duration

(hours)

Turbidity (ntu)

Particles >2 µm per mL

Raw

Treated Water

Sample

Median

Median

Mean

95th

Percent

<2 ntu

1

2

3

4

no polymer

1.1

7.30

11.40

11.43

12.67

0.0

no data

0.25 mg/L

2.0

17.74

0.75

0.72

0.75

100.0

15,169

2,941

2,374

2,097

0.50 mg/L

4.6

28.19

0.89

0.87

0.96

100.0

1,873

2,306

2,438

3,094

0.75 mg/L

2.0

18.84

0.89

0.88

0.96

100.0

6,480

5,241

6,677

 

1.00 mg/L

2.6

19.81

0.62

0.64

0.69

100.0

4,827

 

 

 

 

Note:  12 gpm/ft2 Loading Rate, 2.6 percent recycle

 

Figure B.22  Morgan WTP SFBW DensaDeg impact of polymer dose on SFBW


Option D would retrofit the existing 7,000 ft2 clarifier system with two 5,100 gpm DensaDeg Systems to meet new SFBW production targets. The new system would have a total footprint of approximately 110 ft by 30 ft or 3,300 ft2 as depicted in Figures B.23 to B.26.  The retrofit would involve renovation of the existing building to include raising the clarifier roof, demolishing existing basin walls, constructing DensaDeg basin walls, and adding necessary equipment.  DensaDeg cost calculations are summarized in Tables B.13 and B.14. Costs include construction of new concrete roof, DensaDeg basin walls, DensaDeg equipment, instrumentation, controls, and pumps.

 

 

Table B.13

10 percent SFBW recycle EQ and DensaDeg retrofit cost analysis

ITEM

Capital cost

($)

O&M cost

($/yr)

20-yr present worth

($)

New EQ basin (44-ft diameter)

2,453,000

43,000

2,944,000

DensaDeg system retrofit (3300 ft2)

11,000,000

225,000

13,500,000

TOTAL PROJECT COST

13,453,000

268,000

16,444,000

 

 

Table B.14

5 percent SFBW recycle EQ and DensaDeg retrofit cost analysis

ITEM

Capital cost

($)

O&M cost

($/yr)

20-yr present worth

($)

New EQ basin (93-ft diameter)

4,740,000

75,000

5,604,000

DensaDeg system retrofit (3300 ft2)

11,000,000

225,000

13,500,000

TOTAL PROJECT COST

16,740,000

300,000

19,104,000


0322 IDI Densadeg 5100gpm PlanviewProvided by Infilco-Degremont, September 2007

 

Figure B.23  Morgan WTP SFBW DensaDeg 5,100 gpm system plan view

0322 IDI Densadeg 5100gpm ProfileProvided by Infilco-Degremont, September 2007

 

Figure B.24  Morgan WTP SFBW DensaDeg 5,100 gpm system profile view

0322 IDI Densadeg 5100gpm P&IDProvided by Infilco-Degremont, September 2007

 

Figure B.25  Morgan WTP SFBW DensaDeg 5,100 gpm system P&ID

Provided by Infilco-Degremont, September 2007

0322 Morgan Densadeg System GA

Figure B.26 Morgan WTP SFBW DensaDeg system general arrangement